Banyo pedestrian footbridge project

April – October 2017

Queensland Rail will install a new pedestrian footbridge at the northern end of Banyo station to improve customer safety and cross-corridor access.   

The footbridge will be constructed off-site and installed at the northern ends of the Banyo station platforms, and will include anti-climb privacy screens, Crimsafe security and anti-throw screens as well as new signage, lighting and security cameras.

Work commenced in late April, with completion expected by mid-October 2017, weather and construction conditions permitting.

During this time there will be temporary changes to station access at the northern ends of the platforms to facilitate the installation of the concrete support structures.

Resources

Project Fact Sheet ( PDF | DOC)

Early morning concrete works - June 2017 (PDF | DOC)

Night works and concrete works - July 2017 (PDF| DOC)

Bridge installation 25-26 September 2017 (PDF | DOC)

Contact

We are committed to keeping customers and the community informed. 

For more information about the Banyo pedestrian footbridge project, call 13 16 17 (8am to 5pm Monday to Friday), or email communityengagement@qr.com.au